Bathroom Subfloor & Tile, Lancaster

Project Spotlight · Lancaster, Ohio

Bathroom Subfloor Repair & Retile in Lancaster, Ohio

Rotted Subfloor Replaced, New Tile Installed

What started as a simple bathroom update turned into a subfloor repair once we found rot around the toilet. We replaced the damaged subfloor, installed cement board, laid new tile, and finished the room with a new toilet, faucet, trim, and vanity paint.

NewSubfloor & Cement Board
NewTile Floor
NewToilet & Faucet
The Project

A Bathroom Update That Uncovered Subfloor Rot

This Lancaster homeowner called us for a bathroom update: new paint, a new faucet, a new toilet. Once we pulled the old flooring up around the toilet, we found the subfloor underneath had rotted out.

We cut out and replaced the damaged section of subfloor, installed cement board to properly support new tile, laid the new tile floor, set a new toilet, and finished the room with new white baseboard trim, a repainted vanity, and a new faucet.

Project Details

At a Glance

Subfloor repair, cement board, new tile, new toilet, new trim, and a repainted vanity, a bathroom that’s solid underneath and finished on top.

Finished bathroom with new tile floor, new toilet, and repainted vanity, Lancaster, Ohio
Location
Lancaster, Ohio
Service
Subfloor Repair & Tile Install
Included
Subfloor, Cement Board, Tile
Also Included
New Toilet, Faucet & Trim
Result
Solid, Fully Retiled Bathroom
The Problem

Rotted Subfloor Hiding Under the Toilet

Once the old flooring came up, we found the subfloor around the toilet had rotted, not something that shows up until you actually open the floor up. Tiling over it would have meant a soft, failing floor down the road.

The Fix

New Subfloor, Cement Board & Tile

We cut out the rotted section, replaced it with new subfloor, and installed cement board over the whole area so the new tile has a solid, stable base. Then we laid the tile, set a new toilet, and finished the room out.

Why This Matters

Why We Always Check the Subfloor First

Water around a toilet or tub finds its way down before you ever see a stain upstairs. Tiling over a damaged subfloor just buries the problem. It’ll show up later as cracked grout, loose tile, or a floor that feels soft underfoot. Checking the subfloor before any tile goes down is what makes the finished floor last.

Noticed a soft spot, loose tile, or a musty smell near your bathroom floor? We can check the subfloor and give you a straight answer before anything gets covered up.

From Rot to Retiled

Subfloor Repair to Finished Floor

This Lancaster bathroom, from the rotted subfloor to the finished tile and fixtures.

Rotted subfloor around the toilet before repair, Lancaster, Ohio
Before: Rotted Subfloor
New toilet flange set into the new plywood subfloor patch, Lancaster, Ohio
New Subfloor & Flange
Plywood subfloor repair patch installed around the toilet area, Lancaster, Ohio
Subfloor Patch Installed
Cement board tile underlayment installed over the new subfloor, Lancaster, Ohio
Cement Board Underlayment
Closeup of cement board screwed down near the toilet flange, Lancaster, Ohio
Cement Board Detail
Full cement board installation ready for tile, Lancaster, Ohio
Ready for Tile
New tile being installed with thinset and spacers, Lancaster, Ohio
Tile Going In
Finished new tile floor with spacers still in the grout lines, Lancaster, Ohio
New Tile Floor
New toilet installed on the finished tile floor, Lancaster, Ohio
New Toilet Installed
Bathroom Subfloor Repair in Lancaster, OH

Bathroom Subfloor Repair & Retile in Lancaster, OH

From a damaged subfloor to a fully retiled bathroom, we handle subfloor repair, tile installation, and bathroom updates of every size throughout Lancaster and Fairfield County.

Lancaster & Fairfield County

Ready to Fix Your Bathroom Floor?

Request an estimate, or text us a few photos of the floor for a quick ballpark.

Subfloor Repair Tile Installation Bathroom Updates Water Damage Lancaster, Ohio

Bathroom Subfloor Repair FAQs

A soft or bouncy feel near the toilet or tub, a musty smell, or cracked grout and loose tile are the usual signs. On this project, we found the rot once we pulled up the old flooring to start the update.

Usually just the damaged section. We cut out the rotted area and tie in new subfloor material, like we did around this toilet, rather than tearing out the whole floor.

Cement board gives tile a stable, water-resistant base that won’t flex or absorb moisture the way plywood alone would. It’s what keeps grout lines from cracking down the road.

A subfloor repair with a full retile, like this one, typically runs three to five days depending on the size of the area and how much subfloor needs replacing.

We’ll stop and walk you through exactly what we found and what it takes to fix it before doing any additional work, so there are no surprises on the bill.

Yes, on this project we installed a new toilet and faucet, added new white baseboard trim, and repainted the vanity along with the subfloor and tile work.